News

News

[I-924/I-526 Approved EB-5 Project] Seattle Southport Office June 2019 Construction Update

Permits – Office:

Permit B15005268 – Underground Work and Podium/Garage – Issued

Permit W16000521 – Hydrant Meter – Issued

Permit B16000394 – Underground Work – Issued

Permit B16002140 – Johns Creek Bridge – Issued

Permit U16002823 – Johns Creek Bridge Utilities – Issued

Permit U15005273 – Plumbing – Issued

Permit W17000191 – Irrigation Meter – Issued

Permit E16005077 – Electrical – Issued

Permit F16004945 – Fire Alarm – Issued

Southport Office Construction Site 06/27/2019

 

Tower 1 and Tower 2 Construction operations have completed for both. The City of Renton granted permission to occupy on 06/11/2019.

Southport Office Tower 1 and 2

 

Courtyard between Tower 1 and 2

 

Tower 3 continues to move forward towards a completion third quarter of 2019.

Southport Office Tower 3 Construction Site

 

Interior finishes  are in the final stage of completion for office levels 4 through 9, with the plumbers installing water fountains, sinks and faucets. Ceiling installation has begun at level O1. Completion of the ceiling will allow for commencement of installation of podium interior finishes.

Water Fountains

 

The Pavilion and courtyard finishes construction between towers 2 and 3 has commenced.

Pavilion and Courtyard between Towers 2 & 3

 

Campus-wide sitework made real progress.  With the completion of the Sanitary Sewer replacement project we were able to substantially complete the sidewalk, pave roads, and begin lane markings this month.  July will see the completion of the exterior hardscape and continued installation of landscaping.

Campus-wide Sitework